Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Date

Attendees

Prakash Ramchandran

Goals

  • Review of LFN GB meeting/Approvals
  • Discuss path forward, including meeting schedule, sub team selections

...

TimeItemWhoNotes
10 MinReview of LFN GB presentation and acceptance
  • GB accepted Merger/Re-imagine option and agreed to support Re-branding
    • Cédric Ollivier mentioned that the 2 questions merged in one to the LFN Board should have been asked separately (only the option was part of the community consensus)
    • William DIEGO (Orange) expressed concern over re-branding question.
    • Cédric Ollivier we discussed an LFN edit in between community discussions and the LFN Board meeting
 30 Min

Discuss the Oversight Committee & Sub Teams

Solicit Volunteers for Sub teams

10 MinOverview of Trust and Team building program
  • Topics
    • Acceptance
    • Expression
    • Trust
10 MinDiscuss schedule and Participation
  • Sub teams will set their own meeting schedule and method of interaction
  • Oversight Committee Meeting day and time?

...