Goals:
- Integration tests in target deployments using OOM.
- Writing E2E tests for the Workflow designer.
- Improving SDC test unit test coverage: BE/FE.
- Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium.
- Moving to Junit 5 syntax where possible.
- Improving and standardize the test code of SDC.
...
# | Activity | DueDate | Status | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
1 | Set up the development environment, running locally, getting familiar with the SDC portal as well as testing Environment. |
|
| ||||||||
2 | Writing E2E tests for the Workflow designer. |
|
| ||||||||
3 | Improving SDC test unit test coverage: BE/FESolving the issue SDC-3181 broken workflowD. |
|
| ||||||||
4 | Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium. |
|
| ||||||||
5 | Moving to Junit 5 syntax |
|
| ||||||||
6 | Writing an integration test in the Robot framework (CSIT) for OOM gating. |
|
| ||||||||
7 | Improving and standardize the test code of SDC. |
|
| ||||||||
8 | User guide or other development delivery documents. |
|
|
Deliverables:
- Robot or java test that covers also the Workflow Designer plugin.
- More Tests on SDC BE/FE platforms.
- Integration Tests on OOM gating with RobotFramework.
Status colour Yellow title Pending - Improved SDC CSIT(selenium) stability with upgraded selenium.
- Moved to JUnit 5 on all tests.
Evaluation Criteria:
- 1st Evaluation (end of week 3): Good Understanding of project, familiar with the dev - environment, SDC portal. know well about SDC testing frameworks and its tests
- 2nd Evaluation (end of week 6): Finished tests on E2E for the workflow Designer and SDC BE/FE test coverage.
- 3rd Evaluation (end of week 9): Finished improving SDC CSIT stability with upgraded selenium, and all the code to the Junit5 syntax.
- Final Evaluation (end of week 12): Finish the OOM gating integration test with documentation.
...