Agenda and Minutes:
- Agenda Bashing
- Approved.
- Botrange Technology Status & planning (Ref M):
- Ch01: Beth
- Editing is ongoing for open issues.
- PR is expected EoEnd of this week.
- Ch02: Ahmed:
- Ahmed to create a PR to address existing issue.
- PR to be created end of Week.
- Ch03: Bernard
- Check if more work is needed and close duplicate issues.
- Proposed PR is expected for Container support.
- Ch04: Mark S
- Revisit issue and confirm Botrange release label.
- 2 PR active.
- Ch05: Karine
- 2 PR is active.
- Storage Issue might have to defer to future releases.
- Ch06: Pankaj
- 1 PR is active.
- still some issues to resolve around the txting of PR.
- Ch07: Walter
- 1 PR is active.
- 2 issues were resolved this week.
- Ch08: Mike F:
- Recurring Ch 8 meeting today
- 1 PR related to Annex
- Progress made on pre-existing 4 Botrange issues
- Will review 5 new issues with Botrange labeled opened overnight 9/10
- Discussion planned during Ch 8 meeting with Orange about OpenStack gates and test frameworks
- Ch09: Tom:
- 1 active PR.
- Ch10: Jonathan
- PRs to be created next week.
- Ch01: Beth
- Botrange Technology Status & planning (Ref A):
- Ch01: Intro
- Ch02: Requirement"
- Ch03: High Level
- Ch04: Component Level
- Antwrep logistics
- schedule and sessions.
- CNTT Developer F2F Workshop, Sept '19Technical F2F Work Shop, Antwerp, Belgium, September 26-27, 2019
- AOB