Project Plan- ONAP Automation Testing-Portal/SDC

Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

Version 1 Next »

Goals:

  1. Integration tests in target deployments using OOM.
  2. Writing  E2E tests for the Workflow designer.
  3. Improving SDC test unit test coverage: BE/FE.
  4. Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium.
  5. Moving to Junit 5 syntax where possible.
  6. Improving and standardize the test code of  SDC.

Tasks:

#ActivityDueDateStatus
1Set up the development environment, running locally, getting familiar with the SDC portal as well as testing Environment.

 

ACTIVE

2

Writing  E2E tests for the Workflow designer.

 

PENDING

3Improving SDC test unit test coverage: BE/FE.

 

PENDING
4Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium.

 

PENDING

5

Moving to Junit 5 syntax

 

PENDING

6

Writing an integration test in the Robot framework  (CSIT) for OOM gating.

 

PENDING

7

Improving and standardize the test code of  SDC.

 

PENDING

8User guide or other development delivery documents.

 

PENDING

Deliverables:

  1.  Robot or java test that covers also the Workflow Designer plugin.
  2. More Tests on SDC BE/FE platforms.
  3. Integration Tests on OOM  gating with RobotFramework.
  4. Improved SDC CSIT(selenium)  stability with upgraded selenium.
  5. Moved to JUnit 5 on all tests. 

Evaluation Criteria:

  • 1st Evaluation (end of week 3):  Good Understanding of project, familiar with the dev - environment,  SDC portal. know well about SDC testing frameworks and its tests
  • 2nd Evaluation (end of week 12): Finished tests on E2E for the workflow Designer and SDC BE/FE test coverage.
  • 3rd Evaluation (end of week 9): Finished improving SDC CSIT stability with upgraded selenium, and all the code to the Junit5 syntax.
  • Final Evaluation (end of week 12): Finish the OOM gating integration test with documentation.