Goals:
- Integration tests in target deployments using OOM.
- Writing E2E tests for the Workflow designer.
- Improving SDC test unit test coverage: BE/FE.
- Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium.
- Moving to Junit 5 syntax where possible.
- Improving and standardize the test code of SDC.
Tasks:
# | Activity | DueDate | Status |
---|---|---|---|
1 | Set up the development environment, running locally, getting familiar with the SDC portal as well as testing Environment. |
| |
2 | Writing E2E tests for the Workflow designer. |
| COMPLETE |
3 | Solving the issue SDC-3181 broken workflowD. |
| COMPLETE |
4 | Improving SDC CSIT (Selenium) coverage and stability, upgrading to a more recent version of Selenium. |
| PENDING |
5 | Moving to Junit 5 syntax |
| PENDING |
6 | Writing an integration test in the Robot framework (CSIT) for OOM gating. |
| COMPLETE |
7 | Improving and standardize the test code of SDC. |
| PENDING |
8 | User guide or other development delivery documents. |
| COMPLETE |
Deliverables:
- Robot or java test that covers also the Workflow Designer plugin.
- More Tests on SDC BE/FE platforms.
- Integration Tests on OOM gating with RobotFramework.
- Improved SDC CSIT(selenium) stability with upgraded selenium.
- Moved to JUnit 5 on all tests.
Evaluation Criteria:
- 1st Evaluation (end of week 3): Good Understanding of the project, familiar with the dev - environment, SDC portal. know well about SDC testing frameworks and its tests
- 2nd Evaluation (end of week 6): Finished tests on E2E for the workflow Designer and SDC BE/FE test coverage.
- 3rd Evaluation (end of week 9): Finished improving SDC CSIT stability with upgraded selenium, and all the code to the Junit5 syntax.
- Final Evaluation (end of week 12): Finish the OOM gating integration test with documentation.
Work Due
- Shifting all the Junit 4 tests to JUnit 5(half of it is already done by the SDC team)
- upgrading the selenium to the newest version in existing tests.
Workflow
- SDC Setup environment stage.
- Workflow Designer integration with SDC.
- Started Learning RobotFrameWork and selenium to create the tests.
- Wrote the test for the workflow designer and SDC.
- Wrote the scripts to integrate the tests with the CSIT repository.
- Submitted ticket for the review.
- Started working on the ticket SDC-3181 with the SDC team.
- Writing tests for the SDC with the ONAP portal.
- Started doing set up in my local environment with oom.
- Getting access for the Winlab and started testing my test on the portal
- Solving some problem related to the test
Challenges Faced during the program
- setup problem
- physical instrument restrictions
- complex documentation
- lab access problem
Insight Gained
- learned how to work as a team
- Tackling complex projects
- lot about new technologies
- How to work with a big community.
Documentation:
Full Documentaion of the project can be seen on SDC portal wiki page.