2019-10-30 - [CNTT - Technical Steering] - Meeting Agenda and Minutes

Walter canceled the meeting and has asked for a silent update. Thanks

Attendees:

Please add your name in here:

  • Person 1

  • @Mark Shostak (AT&T)

  • @Pankaj.Goyal (AT&T)

  • @Michael Fix

  • @Al Morton (AT&T)

  • @speedwyre (AT&T)

  • @Gergely Csatari (Nokia)

  • Ahmed Sawaaf (STC)

  • @Toshi Wakayama (KDDI)

  • @Karine Sevilla (Orange)

  • @Prakash Ramchandran (Dell)

Agenda and Minutes:

  • Agenda Bashing

  • WSL Lead, co-lead, contributor assignments and vacancies

  • Jira Site building - status

  • Track Snezka Roadmap Status.

    • RM Core: Created plan to drive new content. Will align on RM Master Meeting in 1 hour.

    • RM Ops: Created plan to drive new content. Will align on RM Master Meeting in 1 hour.

    • RM Comp: RM Comp: Awaiting update from Victor or Rabi (see minutes of 23/10/2019)

    • RA1 Core: 

      • 15 Issues: 1 issue (#260) is really for Governance; Ch2 - 3 issues; Ch 5 - 1 issue

      • Ch3 and 4 - 10 issues. Sub team for Chapter 3 and 4 to meet to decide on content development

    • RA1 Ops:.

      • 3 issues and 2 PRs:

        • issue #371 (APIs) partially adressed by PR #463 (addition of Neutron extensions)

        • issue #455 (security) assigned and discussion started on ToC

        • issue #369 (LCM) addresed by PR #461 (ToC and outline)

      • Feedbacks expected on PR #463 and #461

  •  

    • RA1 Dev: 

    • RA2 Core:

      • 10 issues, 5 assigned

      • 2 PR-s open, to be discussed on the Thursday meeting

    • RA2 Ops:

      • 1 issue open, no activity

    • RA2 Dev:

    • RI1 Core: 

      • Issues:  4 opened, 4 assigned, to be discussed 10/30 during weekly call

      • PRs: 0 opened, 0 need review

    • RI1 Lab: 

      • POD10 (PoC lab) setup and deployment complete, pending verification and validations

      • POD10 review of lesson's learned to be discussed 10/30, and plan for implementation into target POD15 lab

      • Issues:  3 opened, 3 assigned, to be discussed 10/30 during weekly call

      • PRs:  0 opened, 0 need review

    • RI1 Dev: 

      • Slave Jenkins server staged, along with automation jobs for deployment component validations; jobs awaiting execution until confirmation of successful POD10 setup

      • Issues: 8 opened, 5 assigned; the 3 unassigned were recently opened to port/modify test frameworks of Bottlenecks, Yardstick, KloudBuster for CNTT POD10/15 purposes; to be reviewed during 10/30 meeting

      • PRs: 0 opened, 0 need review

    • RC1 NFVI: .

      • Prepare automation harness - connectivity established; pending executions once POD10 confirmed up/working; e.g. functest-smoke-cntt was just created. neutron-tempest-plugin-api is already conformed with the current API section.

      • Test Case requirements identified; however, targeted for RM CH8 Comp sections (PR to be generated and inserted- pending confirmation complete)

      • Issues:  5 opened, 5 assigned; status to be covered during 10/30 weekly call

      • PRs:  0 opened, 0 need review

    • RC1 VNF: 

      • Discussion of VNF Family/Prototypes via email last week; initial strategy is to use POD10 Network Intensive profiles, evaluate, then discuss Compute and Storage profile evaluations

      • Further discussion on above strategy, plan, and timeline during 10/30 weekly call

      • Issues: 6 opened, 6 assigned; status to be covered during 10/30 weekly call

      • PRs: 0 opened, 0 need review

    • RC1 Dev: 

      • Similar to RI1 Dev - Slave Jenkins server staged, along with automation jobs for deployment component validations; jobs awaiting execution until confirmation of successful POD10 setup

      • Issues: 14 opened, 12 assigned; the two unassigned were recently opened for the porting of Bottlenecks and Yardstick for CNTT POD10 PoC testing

      • PRs: 0 opened, 0 need review

  • AOB