2019-11-06 - [CNTT - RC - 01] - Meeting Agenda and Minutes

2019-11-06 - [CNTT - RC - 01] - Meeting Agenda and Minutes

Attendees:

Please add your name in here:

  1. @Michael Fix

  2. @Ashok Kumar (VoerEir)

  3. @Mark Shostak (AT&T)

  4. @Deepanshu Bhatia (VoerEir)

  5. @Manik Sidana (VoerEir)

  6. @Vaibhav Chopra (Orange)

Goals of the 11/06 Meeting

  • RI POD10 Manifest validations, and POD15 Target

  • RC Issues Log, Documentation Status, Automation Harness, VNF Prototype Test Planning

Agenda and Minutes:

  • Agenda Bashing

  • Antitrust: https://r.lfnetworking.org/Antitrust%20Slide.pdf

  • RI: status

    • CNTT-RI Project Name Change → Common Infrastructure Realization & Validation (CIRV)

    • Labs status - setup, automation

      • Discussed PR 535 as a start for Installer Requirements

      • Discussed need for RI (as well as RC) and Run Book documentation to be delivered with Jan F2F

      • See complete minutes from RI meeting.  CNTT - RI - 01

    • Tracking:

    • PR to review:  535 discussed and reviewed, along with general push for team members to review open PRs and approve

  • RC: status

    • Status | Milestones - CNTT Snezka (next CNTT release)

    • RC WS Status | Issues

      • NFVI

      • VNF

      • Dev → Volunteers for Dev new issues by Cedric?

  • AOB

 

Status | Milestones:

  • General

  • Work-stream

    1. NFVI (Lead = Rajesh, Mike)

      1. IssuesPRs

      2. Assistance Needed

        (In progress) RA 1 requirements extraction → Rajesh, work with Mark S., Sridhar  → work in progress
        (In progress) Manifest validations vs. RA Req → discussed in the RI work stream call, work in progress as AirShip manifests were followed for installs, but confirmation needed to ensure RA requirements have been met; offline discussion happening in email to confirm if manifest require changing
        Tune the declarative files to meet RA requirements (re-deploy)
      3. Status | Tasks (Work in progress)

        Receive Lab (date)
        (In progress) Translate RA requirements to Manifest Needs (date)
        Tune Manifest to match RA requirements (Target End State Lab - POD15) - status of POD 10, then date for POD 15

        Testing

    2. VNF (Lead = Mike)

      1. IssuesPRs

      2. Assistance Needed

        1. Empirical Validations - VNF Prototype Plan / Strategy

        2. Trevor - details / dates for Network profiles and testing

      3. Status | Tasks (Work in progress)

        1. VNF Prototypes

          (In Progress) Families Identified
          (In Progress) Test Requirements Identified

          Strategy

        2. Testing

          1. Create Test Plan

          2. Finalize Test Harness/Framework

          3. Results Collection & Normalization

    3. Dev (Lead = Cedric)

      1. IssuesPRs

      2. Assistance Needed

        1. Deployment Validations and continuous deployment / integration 

      3. Status | Tasks (Work in progress)

        1. Jenkins setup

        2. VNF prototype

          1.  Development

          2. Connectivity to POD15

AOB:

  1. Item 1

  2. Item 2

  3. Item 3

Notes:

Actions:

  • 11/06 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 13, 2019  
    Owner: Rajesh - determine a target date for POD15 installs, taking into consideration POD10 install completion, manifest validations, and API health/smoke tests, being done BEFORE POD15 installs by Nov 1, 2019 
    Owner: Mark (Victor) - Setup call to start Tracing RM Comp to RC Chapter sections by Nov 1, 2019 
    Owner: Fu Qiao - identify how to incorporate, or start developing, PDF and SDF consumables by Nov 1, 2019 
    Owner: Leads - Review / Add Milestones to the Minutes in the Appropriate 'Status | Milestones' section by Nov 8, 2019 
  • 10/30 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 6, 2019 
    Owner: Rajesh - get current status from Srihdar on POD10 installs, and open a GitHub issue to track the deployment by Nov 1, 2019 
  • 10/23 Meeting

    Owner: All →Review/respond to GitHub issues by Oct 29, 2019
    Owner:  Leads - Assign / work action items by EOW Oct 25, 2019 
    Owner: Rajesh - Meet w/ Trevor + others to discuss overall CNTT Lab Requirements (needs - e.g. POD10, 15, 17-18 (AirShip), 19-Test Tools, etc) by Oct 23, 2019 
    Rajesh (host), Trevor, Mark, and Mike - met to discuss the Intel labs and their intended use; acknowledge 10/15/19 are used for CNTT PoC/TargetState/TestTools labs.  17 and 18 are being used by the Airship project, but not CNTT.  Next steps are to research the availability of a 2nd lab within Spirent, and to attend upcoming LF Lab Planning Sessions for future lab needs/support.
    Owner: Cedric - open a GitHub issue for the setup of the Jenkins hosts for RI validation by Oct 23, 2019 
  • 10/16 Meeting:  Yielded time to RI Kickoff discussions.  Refer to RI meeting notes for 10/16 for details

    Setup recurring call for RC series starting 10/23
  • 10/9 Meeting

    Owner: All → Review/respond to GitHub issues by Oct 16, 2019 
    Owner: Impacted Individuals (Test, Installer, Support) - needing access to POD15, request/receive access by Oct 16, 2019   
    Owner: Mike - confirm with Cedric O. (Orange) if he will be the "lead" to centralize Implementation & Adoption of Test Hardness/Framework efforts on/by Oct 11, 2019 
    Owner: Rajesh - confirm with Sridhar (Spirent) if he will be the "lead" to centralize s/w deployments on/by Oct 11, 2019