2019-11-20 - [CNTT - RC - 01] - Meeting Agenda and Minutes

2019-11-20 - [CNTT - RC - 01] - Meeting Agenda and Minutes

Attendees:

Please add your name in here:

  1. @Michael Fix

  2. @Mark Shostak (AT&T)

  3. @Ashok Kumar (VoerEir AB)

  4. @Pierre Lynch [Keysight] (Keysight)

  5. @Mark Beierl (VMware)

  6. @Rajamani, Rajesh (Spirent)

  7. @Cédric Ollivier (Orange)

  8. @Daniel Balsiger (Swisscom)

  9. @Justin Higa (Spirent)

  10. @Liang Chen (China Mobile)

  11. @Lincoln Lavoie (UNH-IOL)

  12. @Jiaqiang Zhang (China Mobile)

  13. @Lei Huang (China Mobile)

  14. @Rabi Abdel (Vodafone)

  15. @Rajamani, Rajesh (Spirent)

  16. @Kanag (Huawei)

  17. @Shiby Parayil (IConectiv)

  18. @Trevor Cooper (Intel)

  19. @Yan Yang (China Mobile)

  20. @Jiaqiang Zhang (China Mobile)

Goals of Meeting

  • Agenda Bashing

  • Antitrust: 

  • Volunteer Commitment to work on Chapters

    • Status (11/20)

      • Meet with contributing partners - goal for each Chapter team, and discuss goals and timeline for writing the documentation

      • TOC by EOW - Mike will assist, and ask leads to update

  • Prototype Plan (Trevor)

    • Status (11/20)

      • Weekly meetings occurring (Sridhar, Trevor, Luc/Petar, others) - discussing build-out and use of a basic VNF prototype (ETA pending for completion and detailed plans)

      • For VNF Prototype Testing:

        • We can Leverage SampleVNF projects (and VNFs) for establishing baseline results of NFVI operability/stability

        • Can also use 4x Functest VNFs (for benchmarking purposes)

      • StorePerf can be used for storage based evaluating

  • Deployment and Compliance Validation (Cedric) > covered in RI discussions

  • RM/RA requirements extraction (Rajesh, Sridhar) >covered in RI discussions

  • Time Permitting

    • Issue Updates

*****************************

Detailed Agenda and Minutes:

  • Status: 11/20

    • Team members were added, and partnered to assist with the creation of the chapter material

    • Mike to request each team reach across and start collaborative discussions to create content, starting with a Table of Contents (TOC) by EOW (11/22)

  • RC: status | issues

    • NFVI

      • Ch01: Introduction: Rajesh, Kanagaraj, Manik (confirmed)

      • Ch02: NFVI E2E C&V Framework Requirements: Cedric, Manik (confirmed)

      • Ch03: NFVI Test Case Requirements: Georg, Toshi , Deepanshu 

      • Ch04: NFVI TC Traceability to RA Requirements: Rajesh, Dan, Ashok

        • SME: Functest knowledge

    • VNF

      • VNF Prototype Plan - details, dates (Trevor)

      • Ch05: VNF E2E C&V Framework Requirements:  Kanagaraj, Cedric, Shiby (confirmed)

      • Ch06: VNF Test Case Requirements: Fu Qiao, Yan Yang (confirmed), Chuyi Guo, Kanagaraj, Shiby (confirmed)

      • Ch07: VNF TC Traceability to RM Requirements: Rajesh, Kanagaraj, Yan Yang (confirmed)

        • SME: Functest knowledge

    • Dev

      • Deployment Validations (Cedric)

      • Ch08: E2E Framework Integration: Cedric, Kanagaraj, Sridhar  Yan Yang (confirmed)

      • Ch09: NFVI Tests Traceability to TC Requirements: Cedric

      • Ch10: VNF Tests Traceability to TC Requirements: Cedric, Liping Zhao , Shiby (confirmed)

      • Ch11: Gap analysis & Development: Cedric, Kanagaraj, Shiby (confirmed)

  • AOB

 

Status | Milestones:

  • Work-stream

    1. NFVI (Lead = Rajesh, Mike)

      1. Issues:  6 open

      2. PRs: 0 open

      3. Assistance Needed

        (In progress) 11/13 - Sridhar/Rajesh/Mark shifting ownership to RM/RA 1 team for extraction → Rajesh, work with Mark S., Sridhar  → work in progress
        (In progress) Manifest validations vs. RA Req → discussed in the RI work stream call, work in progress as AirShip manifests were followed for installs, but confirmation needed to ensure RA requirements have been met; offline discussion happening in email to confirm if manifest require changing
        Tune the declarative files to meet RA requirements (re-deploy)
      4. Status | Tasks (Work in progress)

        Receive Lab (date)
        (In progress) Translate RA requirements to Manifest Needs (See above for Assistance needed)
        Tune Manifest to match RA requirements (Target End State Lab - POD15) - status of POD 10, then date for POD 15

        Testing

    2. VNF (Lead = Mike)

      1. Issues: 6 open

      2. PRs: 0 open

      3. Assistance Needed

        1. Empirical Validations - VNF Prototype Plan / Strategy

        2. Trevor - details / dates for Network profiles and testing

      4. Status | Tasks (Work in progress)

        1. VNF Prototypes

          (In Progress) Families Identified
          (In Progress) Test Requirements Identified

          Strategy

        2. Testing

          1. Create Test Plan

          2. Finalize Test Harness/Framework

          3. Results Collection & Normalization

    3. Dev (Lead = Cedric)

      1. Issues: 15 total open

      2. PRs: 0 open

      3. Assistance Needed

        1. Deployment Validations and continuous deployment / integration 

      4. Status | Tasks (Work in progress)

        1. Jenkins setup

        2. VNF prototype

          1.  Development

          2. Connectivity to POD15

AOB:

  1. Item 1

  2. Item 2

  3. Item 3

Notes:

Actions:

  • 11/20 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 27, 2019   
    Owner: Rajesh - determine a target date for POD15 installs, taking into consideration POD10 install completion, manifest validations, and API health/smoke tests, being done BEFORE POD15 installs by Nov 22, 2019 
    Owner: Mark (Victor) - Setup call to start Tracing RM Comp to RC Chapter sections by Nov 15, 2019 
    Owner: Fu Qiao - identify how to incorporate, or start developing, PDF and SDF consumables by Nov 22, 2019  
  • 11/13 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 20, 2019   
    Owner: Leads - Review / Add Milestones to the Minutes in the Appropriate 'Status | Milestones' section by Nov 15, 2019 
  • 11/06 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 13, 2019  
  • 10/30 Meeting

    Owner: All →Review/respond to GitHub issues by Nov 6, 2019 
    Owner: Rajesh - get current status from Srihdar on POD10 installs, and open a GitHub issue to track the deployment by Nov 1, 2019 
  • 10/23 Meeting

    Owner: All →Review/respond to GitHub issues by Oct 29, 2019
    Owner:  Leads - Assign / work action items by EOW Oct 25, 2019 
    Owner: Rajesh - Meet w/ Trevor + others to discuss overall CNTT Lab Requirements (needs - e.g. POD10, 15, 17-18 (AirShip), 19-Test Tools, etc) by Oct 23, 2019 
    Rajesh (host), Trevor, Mark, and Mike - met to discuss the Intel labs and their intended use; acknowledge 10/15/19 are used for CNTT PoC/TargetState/TestTools labs.  17 and 18 are being used by the Airship project, but not CNTT.  Next steps are to research the availability of a 2nd lab within Spirent, and to attend upcoming LF Lab Planning Sessions for future lab needs/support.
    Owner: Cedric - open a GitHub issue for the setup of the Jenkins hosts for RI validation by Oct 23, 2019 
  • 10/16 Meeting:  Yielded time to RI Kickoff discussions.  Refer to RI meeting notes for 10/16 for details

    Setup recurring call for RC series starting 10/23
  • 10/9 Meeting

    Owner: All → Review/respond to GitHub issues by Oct 16, 2019 
    Owner: Impacted Individuals (Test, Installer, Support) - needing access to POD15, request/receive access by Oct 16, 2019   
    Owner: Mike - confirm with Cedric O. (Orange) if he will be the "lead" to centralize Implementation & Adoption of Test Hardness/Framework efforts on/by Oct 11, 2019 
    Owner: Rajesh - confirm with Sridhar (Spirent) if he will be the "lead" to centralize s/w deployments on/by Oct 11, 2019