The first XGVela release plans to be delivered in 2022. Duration will last for 6 months.
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | 2022-05-24 | Start Date | Start Date | Declare Intention: Submit Project Proposal (for new projects) and Project Plan in wiki under projects. |
Initial Checkpoint | 2022-06-07 | Start Date + 2 Weeks | Start Date + 2 Weeks | Initial Checkpoint. All Projects must have completed project plan and get the plan reviewed under TSC meeting. |
Release Integrated deadline | 2022-06-21 | Initial Checkpoint + 2 Weeks | Start Date + 6 Weeks | Deadline for Release Integrated Projects to provide the desired version deliverables for downstream Snapshot Integrated Projects to consume. |
Middle Checkpoint | 2022-09-13 | Start Date + 16 Weeks | Middle Checkpoint for progress of all Projects. | |
Code Freeze | 2022-10-11 | Middle checkpoint + 4 Weeks | Start Date + 20 Weeks | Code freeze for all Projects - cut and lock release branch. |
Final Checkpoint | 2022-10-25 | Code Freeze + 2 Weeks | Start Date + 22 Weeks | Final Checkpoint for all project. |
Formal Release | 2022-11-15 | 6 months after start date | Start Date + 6 months | Formal Release for XGVela. |
...
How to prepare key contents of each event
...
? Please go to Release Process.