Baldy - CNTT Additional Assigned Actions
FEEDBACK INSTRUCTIONS:
The below list published as of 1/23/2020 as a Straw Man. This list requires clarification of WS & allocation of resource assignments. Once Work Stream and or owning Leads are assigned, they requested to update their high-level actions as per the following method.
In the far left column:
Item is targeted for Baldy Release indicate as "Baldy".
Item is targeted for future release, indicate as "Backlog".
Item is not related to a release, indicate as "Other".
Item is not targeted for any release/future release/other, indicate as "Cancel".
Add and or rearrange items in your works stream as is appropriate.
In all other columns
Edit, modify as appropriate for activities listed
Try to keep it high-level (e.g. Agile 'story' level or higher)
14 | OVP (VNFs) | Key Stakeholders | Work Stream | Lead | Target Date | Status | Notes |
---|---|---|---|---|---|---|---|
Backlog | Rethink / Revise to more telco acceptable tests | CNTT, OVP, OPNFV | RC | ||||
Backlog | CNTT Badging Strategy and Design | CNTT, OVP, OPNFV | CSO | @Scott Steinbrueck | RM Ch. 8 | ||
15 | OVP 2.0 (CNFs) | Key Stakeholders | Work Stream (Realigned) | Lead | Target Date | Status | Notes |
Backlog | Need clearer plan here for cloud-based infrastructure | @Scott Steinbrueck | |||||
Backlog |
| OVP, CNTT, CNCF TUG, and regulatory - 3GPP | CSO | ||||
Backlog | Regroup and refine on objectives | OVP, CNTT, CNCF TUG, and regulatory - 3GPP | CSO | ||||
Backlog | Review draft | OVP, CNTT, CNCF TUG, and regulatory - 3GPP | CSO | ||||
Backlog |
| OVP, CNTT, CNCF TUG, and regulatory - 3GPP | CSO | ||||
Backlog |
| OVP, CNTT, CNCF TUG, and regulatory - 3GPP | CSO | ||||
16 | OPNFV 2.0 (Related) | Key Stakeholders | Work Stream | Lead | Target Date | Status | Notes |
Backlog | CNTT Collaborators with OPNFV | Collaborate with OPNFV TSC sub-committee that @Qiao Fuhas formed. | @Scott Steinbrueck @Qiao Fu @Rabi Abdel | ||||
Backlog |
| CNTT, OPNFV TSC | make sure the projects are relevant | ||||
Backlog |
| CNTT, OPNFV TSC | |||||
Backlog |
| CNTT, OPNFV TSC | |||||
Backlog |
| CNTT, OPNFV TSC | To manage transformational requests | ||||
Backlog |
| CNTT, OPNFV TSC | TSC attendance on CNTT calls | ||||
Backlog |
| CNTT, OPNFV TSC | |||||
Backlog |
| CNTT, OPNFV TSC | |||||
17 | Pre-Launch / Field Trials - Alpha Launch Planning - NFVIs | ||||||
17.1 | Onboarding/Adoption(Badging) Journey | Key Stakeholders | Work Stream (Realigned) | Lead | Target Date | Status | Notes |
Baldy | Outline/define of what is needed in initial Field Trials from RC1/OVP (scope & requirements, user journey, launch plan, mvp) | CNTT, OPNFV, OVP, Trial Participants | Adoption | CNTT - TBD Liaison for OPNFV - @Qiao Fu | Feb | Solicit vendors | |
Backlog | Design launch plan | CNTT, OPNFV, OVP, Trial Participants | Adoption
| CNTT - TBD Liaison for OPNFV - @Qiao Fu | Feb | ||
Backlog | Initial test-badging aligned with CNTT/OVP expectations | CNTT, OPNFV, OVP, Trial Participants | Adoption
| CNTT - Liaison for OPNFV - @Qiao Fu | Mar | ||
Backlog | Provide formalized lab and test cases to participants | CNTT, OPNFV, OVP, Trial Participants | Adoption
| CNTT - Liaison for OPNFV - @Qiao Fu | Mar | MVP | |
17.2 | Infrastructure / Lab Support ("Back Office") | Key Stakeholders | Work Stream (Realigned) | Lead | Target Date | Status | Notes |
Baldy | Secure lab participation/capacity/diversity for initial Field Trials | CNTT, OPNFV, OVP, Labs, Trial Participants | Adoption | Feb | |||
Baldy | Define MVP support model / structure for trials | CNTT, OPNFV, OVP, Labs, Trial Participants | Adoption | Mar | |||
17.3 | Trial Participation | Key Stakeholders | Work Stream | Lead | Target Date | Status | Notes |
Baldy | Confirm trial participants and SPOCs | CNTT, OPNFV, OVP, Trial Participants | Adoption | Jan | RedHat, Ericcson, Nokia, Cononical, VMWare | ||
Baldy | Define expectations, what's needed, roles & responsibilities | CNTT, OPNFV, OVP, Trial Participants | Adoption | Feb | |||
Baldy | Kickoff Meeting / Preparations | CNTT, OPNFV, OVP, Trial Participants | Adoption | Feb | |||
17.4 | Value Demonstration / Activities | Key Stakeholders | Work Stream | Lead | Target Date | Status | Notes |
Backlog | Define consistencies needed | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - add to Recruiting, Engagement, & Adoption Scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective (i.e. "Infographic") | Feb | Effort/how long to turn up / turn down? # of TC failures reported, etc. | |
Backlog | Cookbook validation (usage, steps, etc.) | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - add to RI scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective | Mar | Goal is reduce friction in lab & test onboarding process - based on feedback from Trials | |
Backlog | Capture defect reduction benchmarks / define targets (Capture between Baldy and following release) | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - add to Business | Tech Metrics scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective | Mar | How many NFVI/VVNF initial deploy defects before CNTT? how many defects after? | |
Backlog | Prepare for and perform analysis during trials | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - add to RC scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective | Apr | e.g. recurrance of defects, debugging, engineering and design impacts, duplicative defects, correlative. | |
Backlog | Capture and analyze trial feedback | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - Add to RC/OVP scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective | May | ||
Backlog | Quantify results / benefits / opptys for improvement | CNTT, OPNFV, OVP, Trial Participants | Adoption Proposal - Add Recruitment, Engagement, Adoption scope (Submitted by @speedwyre) | CNTT - Action item - get @Brandon Wick involved from Mktg perspective | May | ||
18 | Beta Launch Planning - VNFs | ||||||
18.1 | Trial Participation | Key Stakeholders | Work Stream (Realigned) | Lead | Target Date | Status | Notes |
Backlog | Recruit and Confirm trial participants and SPOCs | CNTT, OPNFV, OVP, Trial Participants | Adoption | ||||
Backlog | Define expectations, what's needed, roles & responsibilities | CNTT, OPNFV, OVP, Trial Participants | Adoption | ||||
Backlog | Kickoff Meeting / Preparations | CNTT, OPNFV, OVP, Trial Participants | Adoption |