Project Plan - ONAP Modeling/etsicatalog
Goals
1、Implement the part of SDC subscription and notification.
2、Support for the ETSI alignment work.
3、Attend the integration test.
Tasks
# | Activity | Due Date | Status |
---|---|---|---|
1. | Know about whole project and make a research on SDC subscription and notification | Jun 22, 2020 | ACTIVE |
2. | Enhance SDC subscription and notification function | Jul 20, 2020 | PENDING |
3. | Implement SDC direct interface function | Aug 3, 2020 | PENDING |
4. | UT for SDC direct interface function | Aug 17, 2020 | PENDING |
5. | IT for SDC direct interface function | Aug 31, 2020 | PENDING |
6. | Study SOL003\SOL005 and ETSI NFV/NS APIs | Sep 14, 2020 | PENDING |
7. | Implement NFV APIs aligentment with ETSI | Sep 28, 2020 | PENDING |
8. | Implement NS APIs aligentment with ETSI | Oct 12, 2020 | PENDING |
9. | Conduct integration test | Oct 26, 2020 | PENDING |
10. | Development documents and test report | Nov 13, 2020 | PENDING |
Deliverables
Development code for SDC direct interface function.
Development code for API alignment with ETSI SOL specification
Integration test report.
User guide or other development delivery documents
Milestones
Week 6
General understanding and local set up of Modeling/etsicatalog
General understanding the ONAP architecture and main component such as SDC, DMaap, MSB
Research on SDC subscripton & notification
Week 12
Finish the work to enhance the function of SDC direct interface funcation
Development document.
Week 18
General understanding of SOL003\SOL005 and ETSI NFV/NS APIs
Finish the work to API alignment with ETSI SOL specification.
Week 24
Finish the integration test with other components.
Development documents and test report
Evaluation Criteria
1st Evaluation (end of week 6): Good understanding of project goal, etsicatalog framwok. Know well about SDC subscripton & notification functionaliy.
2nd Evaluation (end of week 12): Finish the work to enhance the function of SDC direct interface function.
3rd Evaluation (end of week 18): Finish the work to API alignment with ETSI SOL specification.
Final Evaluation (end of week 24): Finish the integration test with other components, submit IT report.