The first XGVela release plans to be delivered in 2022. Duration will last for 6 months.
Event | Dates | Relative Dates | Start Relative Dates | Description |
---|---|---|---|---|
Release Start | 2022-XX-XX | Start Date | Start Date | Declare Intention: Submit Project Proposal (for new projects) and Project Plan in wiki under projects. |
Initial Checkpoint | 2022-XX-XX | Start Date + 2 Weeks | Start Date + 2 Weeks | Initial Checkpoint. All Projects must have completed project plan and get the plan reviewed under TSC meeting. |
Integrated Projects deadline | 2022-XX-XX | Initial Checkpoint + 2 Weeks | Start Date + 6 Weeks | As this is the first release, this is the period for each project to confirm the version of the projects they want to integrate and they are available to be correctly consumed. Deadline for the confirmation. |
CSIT | ||||
Middle Checkpoint | 2022-XX-XX | Start Date + 16 Weeks | Middle Checkpoint for progress of all Projects. | |
Code Freeze | 2022-XX-XX | Middle checkpoint + 4 Weeks | Start Date + 20 Weeks | Code freeze for all Projects - cut and lock release branch. |
Final Checkpoint | 2022-XX-XX | Code Freeze + 2 Weeks | Start Date + 22 Weeks | Final Checkpoint for all project. |
Formal Release | 2022-11-XX | X months after start date | Start Date + X months | Formal Release for XGVela. |
How to prepare key contents of each event? Please go to Release Process.