CNTT Baldy Release Plan
Goals and objectives: |
|
|
| ||||
Field marketing & campaign plans final | Planned Date | Original Date |
|
|
|
|
|
Baldy release | 5/21/2020 | 5/15/2020 |
|
|
|
|
|
Docs ready | 5/15/2020 |
|
|
|
|
|
|
Go/No-Go | 5/12/2020 |
|
|
|
|
|
|
GA | 5/15/2020 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Deliverable | Due Date | Next Step | Status | Owner | Notes | Jira | Content Link |
Foundational / Core Content |
|
|
| PMM |
|
|
|
PR Announcement messaging | 4/24/2020 |
| 8 Done | Bob | Submitted to Brandon |
|
|
Project messaging | 5/1/2020 | Add to wiki | 8 Done | Nick |
|
|
|
CNTT Datasheet | 5/21/2020 | Determine raw data | 0 Not Started | Nick/Beth |
|
|
|
What's New Deck - Announce | 5/28/2020 | Get raw data from Rabi | 1 In Progress | Rabi/Bob | Webinar deck will serve this purpose. |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Media/Analyst Readiness |
|
|
| Mktg |
|
|
|
Media/Analyst Presentation (Draft) | 5/7/2020 |
| 8 Done | Beth |
|
|
|
Media/Analyst Presentation (Final - if needed) | 5/14/2020 |
| 8 Done | Beth | Presented at several events |
|
|
Media Briefings | 5/14/2020 |
| 8 Done | Beth/Nick/Bob/Scot | Presented at several events |
|
|
Analyst Briefings | 5/28/2020 |
| 8 Done | Beth/Nick/Bob/Scot | Presented at several events |
|
|
Press Release | CANCELLED |
| 0 Not Started | Nick | Replaced with blog post; will do a PR for the fall release |
|
|
|
|
|
|
|
|
|
|
Community/DevRel Readiness |
|
|
| N/A |
|
|
|
Champions lab script & train-the-trainer | 6/4/2020 | Meeting to determine content | 0 Not Started | Bob/Beth/Scot | Needs to follow the field trials |
|
|
Regular newsletter | 6/11/2020 |
|
|
|
|
|
|
Meetup in a Box (deck & demo) | 6/20/2020 | Meeting to determine content | 0 Not Started | Rabi/Bob | Perhaps leverage workstream leads, Scott Steinbreck, Tom Kivlin – OSN meetup groups |
|
|
Recruit workstream leads to do monthly/event-triggered blogs | 6/20/2020 |
|
|
| - Can be supported on the LFN blog |
|
|
|
|
|
|
|
|
|
|
Email Communications |
|
|
|
|
|
|
|
Outreach letter | 5/18/2020 | Determine content | 0 Not Started | Brandon |
|
|
|
Launch Email Blast | 5/21/2020 |
| 0 Not Started | Brandon |
|
|
|
|
|
|
|
|
|
|
|
Launch Virtual Event | Due Date |
| Status |
|
|
|
|
Launch webinar (LFN doing 1 per week) | 5/27/2020 | Determine content | 1 In Progress | Beth/Rabi | Rabi will coordinate with the technical workstreams to bring monthly topics. Rabi will do the first one as a general overlook just before virtual conference (May 27) Bob will help with initial webinar
|
|
|
|
|
|
|
|
|
|
|
Content |
|
|
|
|
|
|
|
CNTT Baldy Release Announcement | 5/21/2020 | Determine content | 1 In Progress | Nick |
|
|
|
Add'l Blog posts: |
|
|
|
| Challenges, gaps, working with other communities |
|
|
- Challenges of multiple architectures | 5/28/2020 | Create draft | 0 Not Started | Shaun/Nick | Aimed at operators |
|
|
- Quantifying savings from faster Network Function onboarding | 6/4/2020 | Create draft | 0 Not Started | Shaun/Nick | Aimed at operators and NFVI vendors |
|
|
- Why we added the Edge workstream (Beth) | 6/18/2020 | Create draft | 0 Not Started | Beth |
|
|
|
- Why RA1 | 6/25/2020 | Create draft | 0 Not Started | Beth |
|
|
|
- Challenges of supporting multiple architectures | 6/30/2020 | Create draft | 0 Not Started | Rabi | Aimed at Network function vendors |
|
|
- How to run the CNTT certification tests | 7/2/2020 | Create draft | 0 Not Started | Cedric | Aimed at vendors (both) |
|
|
Benefit video | 5/21/2020 | Determine content | 0 Not Started | Nick/Bob/Scot/Beth | Aimed at operators |
|
|
Introductory whitepaper | 5/21/2020 | Review draft | 1 In Progress | David Rodewald | Draft expected week of 4/27/20 |
|
|
Brochures & solution briefs (as needed) | 6/20/2020 | Determine need | 0 Not Started | Nick/Bob |
|
|
|