Objectives
Launch update infrastructure badging for VM and CNF infrastructures (RA-1 and RA-2 respectively)
Re-brand under new marketing due to the retirement of the OVP brand
Implement new platform to support registration, submission, review, and badging work (favor off the shelf SaaS over custom built tooling)
The following dates assume a July 2021 release time-frame.
Release Plan
ID | Activity | Description | Owner | Status | Delivery Date | Dependencies |
---|---|---|---|---|---|---|
Anuket Release | ||||||
1 | Requirements Published | Unique, versioned requirements for compliance released. | RA-1/RA-2 | IN PROGRESS | June 2021 | |
2 | Test & Instructions Released | Tests that validate the published requirements along with instructions on how to install, configure, and execute the tests | Functest | IN PROGRESS | June 2021 | |
3 | Test to Requirement Mapping and Instructions | Versioned document that maps tests to requirements, and provides guidance on how to execute the tests to validate conformance. | RC-1/RC-2 | IN PROGRESS | June 2021 | |
OVP Re-Launch | ||||||
4 | Revised Branding Defined | Name, imagery, and other associated copy that will be used in process, marketing, and badging. This should include the versioning strategy for badge (prev. year.month of release) | LF Marketing | IN PROGRESS | May 2021 | |
5 | Revised Process & Platform Defined & Approved | Top-level plan on the process and tooling that will be used to manage the compliance and badging process | CVC | IN PROGRESS | April 2021 | |
6 | Company Registration Process Delivered | Nuts and bolts of how a company will register to submit results for review (including documentation) | CVC | IN PROGRESS | April 2021 | |
7 | Result Submission Process Delivered | Nuts and bolts of how a company will submit test results for review (including documentation) | CVC | NOT STARTED | May 2021 | |
8 | Reviewer Process Delivered | Nuts and bolts of how a reviewer will review test results and provide their vote/feedback | CVC | NOT STARTED | May 2021 | |
9 | Result Publication Process Delivered | Nuts and bolts of how badges will be released and displayed on the public sites. Includes process, destination site, formatting, etc. | CVC | NOT STARTED | June 2021 | |
10 | Reviewers Identified | Identify list of reviewers, and areas they will are signing up to review. Can start with the existing reviewers, but may need revisions. | CVC | NOT STARTED | June 2021 | |
11 | Reviewers Trained | If needed, train any reviewers on the revised process, result formats, and expectations. | CVC | NOT STARTED | June 2021 | |
12 | Initial Candidates Trialed Through New Process | Identify any initial candidates and put them through the process as an initial test case. | CVC | NOT STARTED | July 2021 | |
13 | LF Networking Marketing Site Updates | Update LFN site to support legacy badges, and guide users to new process. Address rebranding, and other marketing copy. | LF Marketing/Staff | NOT STARTED | June / July 201 | |
14 | Press Release | Notify community of release | LF Marketing | NOT STARTED | July 2021 | |